Joint Commissioning Scheme for Photovoltaic Prefabricated Substations and Inverters

16-06 2025

Joint Commissioning Scheme for Photovoltaic Prefabricated Substations and Inverters

1. Introduction

The joint commissioning of photovoltaic (PV) prefabricated substations and inverters is crucial for ensuring seamless integration between power generation units and the grid. This process verifies the coordinated operation of key components, including power conversion, protection systems, and communication interfaces, to meet safety and performance requirements. The following scheme outlines step - by - step procedures, test items, and acceptance criteria for a systematic and efficient commissioning process.

2. Pre - commissioning Preparation

2.1 Equipment Inspection

  • PV Prefabricated Substation:

    • Check the integrity of high - voltage switchgear, transformers, low - voltage distribution equipment, and protection relays.

    • Verify that the substation's rated voltage, current, and short - circuit withstand capacity match design specifications.

  • Inverter:

    • Inspect internal components (IGBT modules, capacitors, cooling systems) for physical damage or loose connections.

    • Confirm the inverter's rated power, maximum power point tracking (MPPT) range, and grid - connection compatibility.

2.2 Document Review

  • Examine installation records, equipment certificates, and wiring diagrams for both the substation and inverter.

  • Ensure compliance with relevant standards (e.g., IEC 62116 for anti - islanding protection, IEEE 1547 for grid - connection requirements).

2.3 Site Condition Verification

  • Confirm that grounding resistance of the substation and inverter is ≤ 4 Ω, as per safety regulations.

  • Check the insulation resistance of power cables and electrical equipment (≥ 10 MΩ for 10kV systems; ≥ 0.5 MΩ for 0.4kV systems).

3. Commissioning Procedures

3.1 Isolated Component Testing

  • PV Prefabricated Substation Tests:

    • Test the functionality of circuit breakers, contactors, and power distribution panels.

    • Measure the voltage and current balance of three - phase outputs.

    • Conduct withstand voltage tests on circuit breakers, isolators, and transformers at 1.1 times the rated voltage for 1 minute.

    • Verify the operation of protection relays (overcurrent, differential, earth fault) by simulating fault conditions.

    • High - voltage Section:

    • Low - voltage Section:

    • Inverter Tests:

      • Perform no - load tests to check the operation of the control system, fan, and display interface.

      • Simulate MPPT operation under different irradiance and temperature conditions to verify power extraction efficiency.

    3.2 Joint System Integration Tests

    • Power Flow Verification:

      • Connect the inverter output to the low - voltage side of the prefabricated substation.

      • Gradually increase the PV array input to the inverter and monitor the power flow from the inverter to the substation, ensuring stable voltage and frequency at the substation's output.

    • Protection Coordination:

      • Trigger fault simulations (e.g., short - circuit, overvoltage) at the inverter or substation side and verify that protection devices (circuit breakers, relays) trip within specified time limits.

      • Test anti - islanding protection by disconnecting the grid connection and confirming that the inverter shuts down within 2 seconds, as required by IEEE 1547.

    • Communication and Monitoring:

      • Check the data exchange between the inverter's control system and the substation's monitoring unit (e.g., via Modbus, CAN bus protocols).

      • Ensure real - time transmission of key parameters (voltage, current, power, temperature) to the central control system.

    3.3 Grid - connection Tests

    • Synchronization Verification:

      • Adjust the inverter's output voltage, frequency, and phase angle to match the grid's parameters.

      • Monitor the inrush current during grid connection; the peak value should not exceed 1.2 times the rated current.

    • Grid - code Compliance:

      • Test the inverter's response to grid voltage fluctuations (e.g., voltage sags, swells) and frequency variations, ensuring it meets grid - code requirements (e.g., maintaining operation within ±10% voltage and ±0.5 Hz frequency deviations).

      • Verify reactive power compensation capabilities by adjusting the inverter's power factor setpoints.

    4. Test Records and Acceptance Criteria

    4.1 Test Records

    • Document all test results, including voltage, current, power measurements, protection device response times, and communication data.

    • Record any abnormal phenomena during commissioning, along with corrective actions taken.

    4.2 Acceptance Criteria

    • Electrical Performance:

      • The voltage deviation at the substation's output should be within ±5% of the rated voltage.

      • The inverter's efficiency should be ≥ 98% under rated load conditions.

    • Protection Functionality:

      • All protection devices (circuit breakers, relays) should operate correctly within specified time - current curves.

      • Anti - islanding protection should detect and isolate the system within the required time limits.

    • Communication and Monitoring:

      • Data transmission between the inverter and substation should be error - free, with a response time ≤ 1 second.

      • The central control system should accurately display real - time operating parameters of both the inverter and substation.

    5. Safety Precautions

    • Ensure all commissioning personnel are trained and equipped with appropriate personal protective equipment (PPE), including insulated gloves, safety helmets, and voltage testers.

    • Isolate power sources before performing any maintenance or testing on live equipment.

    • Establish emergency procedures for handling electrical faults, fires, or equipment malfunctions.

    6. Conclusion

    The joint commissioning of PV prefabricated substations and inverters is a multi - step process that requires meticulous planning, precise testing, and strict compliance with safety and performance standards. By following this scheme, operators can minimize risks, optimize system performance, and ensure reliable grid - connected operation of PV power generation systems.


    Zhejiang Zhilu Transmission and Distribution Equipment Co., Ltd